Eagleridge Creek Restoration and Highway 47 Channel Repairs

Pueblo County, Colorado

Project Details

  • Project Channel Length: 5,000 linear feet
  • Projected Project Cost: $4.4 Million
  • Completion: July 2025 

 

Summary

The Eagleridge Creek Restoration and Highway 47 Channel Repairs Project restored approximately 5,000 linear feet of Fountain Creek near Eagleridge and I-25 in Pueblo County. The project was identified as a priority restoration effort following evaluations completed in 2021 and 2022, which determined that channel stabilization, floodplain reconnection, and removal of abandoned waterline infrastructure were needed to improve creek function and protect nearby infrastructure.

Construction began in Fall 2024 with Holcim as the contractor and funding provided through FCWD’s Monetary Mitigation Funds. The project included channel stabilization, repairs connecting the restoration area to the Highway 47 project, removal of an abandoned waterline and associated infrastructure, installation of two riffle structures to maintain channel grade and reduce sediment loss, and improvements to floodplain connectivity.

During construction, Fountain Creek was temporarily rerouted to allow work on different portions of the project site, including channel improvements and bank stabilization. Despite delays caused by intense summer storms, the project progressed successfully and was completed in August 2025.

Restoration efforts included planting more than 13,000 willow stakes, 125 cottonwoods, and applying hundreds of pounds of native seed to stabilize streambanks, restore riparian habitat, and support long-term ecological resilience. The completed project improves creek function, enhances floodplain connectivity, and protects critical infrastructure along the Highway 47 corridor.

The project was completed approximately $55,000 under budget, demonstrating effective planning, collaboration, and adaptive project management. Recent high-flow events have highlighted the resilience of the restored channel and the success of the restoration approach.

Why This Project ?

Located near Eagleridge and I-25 in Pueblo County, the Eagleridge Focus Area was evaluated in 2021 and 2022 and identified as a priority for restoration. Previous channel instability, limited floodplain connectivity, and abandoned waterline infrastructure reduced the creek’s ability to function naturally and increased risks to surrounding infrastructure.

The project was designed to stabilize Fountain Creek, reconnect the floodplain, and extend the benefits of the Highway 47 restoration work. These improvements reduce erosion, improve riparian habitat, increase flood resilience, and support a healthier watershed for the future.

Colorado College Eagleridge Storyboard

In the Spring of 2024, FCWD partnered with a Colorado College Landscape Processes and Evaluation class and their professor Dr. Sarah Schanz. FCWD Executive Director Alli Schuch provided an introduction to FCWD, its work, and an overview of the Fountain Creek Watershed. Students spent time in the field observing and measuring some of FCWD's projects and developed three storyboards. These storyboards provide an overview and evaluation of FCWD's work around erosion control, the erratic nature of the creek, and thoughts on future projects.  Access the CC Eagleridge Storyboard.